Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Judgment of the Supreme Court of 24 April 2023 (HR-2023-00766-A)

Kortversjonen

This judgment concerns the contractor's obligation to “initiate ordinary proceedings” within eight months of the takeover when he wants to pursue an amendment claim denied by the builder, cf. NS 8407 paragraph 35.2 (b). The same rule can be found in NS 8405 paragraph 26.3, letter b and correspondingly in NS 8415 and NS 8417.

We don't devote a lot of space to account for the background of the case. What can be established is that the eight-month time limit can in the first instance be interrupted by taking out a settlement complaint within the deadline. Normally, a settlement council's consideration of such claims will end with the conciliation board discontinuing the case because it does not have the competence to deal with such complex issues raised by change order claims.

In this case, the Supreme Court ruled that it is not sufficient to file the settlement complaint, have the case adjourned and so need not do anything but take care that the claim is not barred after the ordinary limitation period of three years.

In the judgment, the Supreme Court clearly states that a settlement council case that is suspended must be actively followed up with a subpoena, cf. the condition in NS 8405 paragraph 35.2 (b) that “ordinary proceedings must be instituted”.

Furthermore, the Supreme Court states that the period of eight months in said provision is to be regarded as a limitation period. This means that the contractor must file a lawsuit (in the form of a subpoena) within one year counted from when the case was adjourned in the Conciliation Council. The basis for this is Section 18-3, second paragraph of the Disputes Act, which states the following:

“When the statute of limitations is interrupted by a settlement appeal, this effect ceases if the writ, or any settlement complaint, has not been submitted to the court within one year of the termination of the proceedings by the conciliation board”.

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 875– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

E-kurs

kr 490,–
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 875,– / mnd
Trekkes hver måned
Legg til
  • Tilgang til 79 artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

E-kurs

kr 490,– / mnd
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 300,– / mnd
Trekkes årlig
Legg til
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer