Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

Lytt til artikkelen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

Lytt til artikkelen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

Lytt til artikkelen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

Lytt til artikkelen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

Lytt til artikkelen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Judgment of the Supreme Court of 12.1.2023 (HR-2023-00093-A)

Kortversjonen

This judgment is very interesting and principled for anyone who is either trying to remedy a defect, or to anyone who has a defect that has been tried to be remedied. The principle concerns the extent to which the contractor's remediation attempt in isolation can be perceived as an acknowledgement within the meaning of Section 14 of the Statute of Limitations, and if so, how far the recognition extends.

In this case, the contractor had tried in vain to remedy a deficiency at a newly erected apartment building. It was water-borne heat and the shortage was related to the heating system in the apartments. The contractor assumed that the problems were due to errors in the zoning and operation of the plant.

After the limitation period of three years had expired (counted from the takeover), an expert revealed that the problems were not due to the conditions the contractor had tried to remedy, but that the heating loops had not been insulated in the floor partitions. The consequence was that the underfloor heating did not go up to the floor of the upper floor, but down to the ceiling above the apartment below. In other words, it got too cold on one floor, and too hot on the other floor. Common to all apartments became problematic heat management.

Following its review of a number of judicial source factors on which former judges of the Supreme Court stood centrally, the Supreme Court summarised with the following:

If the contractor has undertaken and/or initiated defect remediation, it may be regarded as an acknowledgement under the statute of limitations section 14, but not necessarily. “The decisive factor will be whether it can be ascertained from the course of action that the debtor has positively and fairly clearly acknowledged the obligation in question.” In other words, an overall assessment of a range of circumstances is required to conclude.

In some cases, the nature and extent of the deficiency may be unclear, but this does not prevent a recognition from being considered to exist. However, the fact that such conditions are unresolved may speak against understanding the entrepreneur's course of action as a realization. In that regard, the Supreme Court highlighted that contractors have a duty to rectify even if they disagree (“jumping duty”).

Finally, the Supreme Court concluded that it is one thing to seek redress of defects, but quite another is to recognize that one is liable for any claim for compensation that a defect may lead to.

In this case, inadequate heat management was not due to the conditions the contractor sought to remedy, but a deliberate choice to drop insulation in the floor partitions. Efforts to remedy this will naturally be substantially more extensive than the remedial experiments with heat management and operation.

After an assessment of the parties' dialogue, agreement documents and other points of the case, the Supreme Court concluded that the contractor had not acknowledged any liability for defects in its course of action. The statute of limitations for the damages claim had not been interrupted by the contractor's remediation attempt.

For both builders and contractors, it is therefore important to observe the limitation period when you have defects that take time to rectify. Care should be taken to either take the necessary legal action or arrange an agreement extending the limitation period for all possible claims the individual circumstances may lead to.

Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår
Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer